Conditional Use Permit
Towns now have authority to approve or disapprove Conditional Use Permits
A conditional use permit (CUP) is an approval by the Dane County Zoning and Land Regulation
Committee and relevant Town Board for certain specific uses listed in the Dane County Zoning
Ordinance. Within each zoning district there are uses that are permitted by right, and other
uses allowed only under certain conditions. A CUP is needed for any use identified in the
zoning ordinance as a conditional use.
After consulting with the Town Clerk or other Town officials, you may apply for a conditional
use permit with Dane County. Requests for conditional use permits must be approved by both your
Town Board and the County Zoning and Land Regulation Committee. The County Zoning Committee
will hold a public hearing on the request, and upon receipt of the written Town Board action
report, will either approve or deny the conditional use permit. Note that either the Town Board
or county zoning committee may deny a conditional use permit. Actions of both the Town Board or
county zoning committee are appealable to the county board. Please refer to the documents at
the top of this page for additional information about the Conditional Use Permit review and
approval process.
Your proposal must comply with each of six standards in the zoning ordinance for a conditional
use permit to be granted, summarized as follows:
- That the conditional use will not endanger the public health, safety, and welfare.
- That uses, values, and enjoyment of other properties in the neighborhood will not be substantially impaired by the conditional use.
- That the conditional use will not impede orderly development of the surrounding property
- That adequate utilities, access roads, drainage, and other necessary site improvements will be provided.
- That adequate measures are being taken to provide ingress and egress to minimize traffic congestion.
- That the conditional use shall comply with all other applicable regulations.
Additional standards apply in the A-1 Exclusive Agriculture District. Consistency with the
recommendations of the Town Land Use or Comprehensive Plan and County Comprehensive Plan will
also be important in the review of your conditional use permit request. Specific conditions may
be required with approval of any conditional use permit.
Expect a minimum of three months between the time you file an application for a conditional use
permit and the time final action on your request is taken.