| Summer 2004 - Winter 2005
|
|
| |
-
Partners sign MOU Addendum's
-
Meet with other interested parties (new partners)
-
Finalize 2005 project plans
|
|
|
|
|
|
| |
|
|
| |
-
Targeting of utilities (as needed)
-
Imagery for Dane County has been captured, reviewed, and accepted for final processing 5/2/05
|
|
|
|
|
|
| |
|
|
| |
| Estimated schedule of deliverables to Dane County LIO (6/2005)
|
|
| |
-
August 2005 - delivery of final control data and reports
-
December 2005 - delivery and review of preliminary imagery
-
January 2006 - delivery and review of terrain data
-
January 2006 - delivery and review of building footprints
-
February 2005 - delivery of final imagery
-
Feb. - March 2005 - distribution of project data to partners
|
| |
|
|
|
|
|
| |